Construction Update: 8th Aug 2019

Progress over period (19/07/2019 – 08/08/2019) Structural demolition of existing ground floor slab On site crushing of hardcore resulted from demolition to minimise vehicle movement Breaking out existing foundations for piling works Installation of Temporary Works to support existing retaining works Excavations works Actions over next period (08/08/2019 – 08/08/2019) Breaking out existing basement slab […]

Read more

Construction Update: 30th January 2019

Progress over period (17/01/2018 – 24/01/2019) Site Set up Erection of hoarding Limited ground clearance Scaffold erection Internal strip-out of buildings Actions over next period (24/01/2019 – 07/02/2019) Completion of hoarding Installation of additional environmental monitoring equipment and hoarding lighting Service isolations and M&E decommissioning continuing within the building Continue scaffolding Continue internal strip out […]