Construction Update: 8th Aug 2019

Progress over period (19/07/2019 – 08/08/2019)

  • Structural demolition of existing ground floor slab
  • On site crushing of hardcore resulted from demolition to minimise vehicle movement
  • Breaking out existing foundations for piling works
  • Installation of Temporary Works to support existing retaining works
  • Excavations works

Actions over next period (08/08/2019 – 08/08/2019)

  • Breaking out existing basement slab to allow piling
  • Crush hardcore material resulted from demolition to minimise vehicle movement
  • Create piling mat
  • Create Pit Lane after Bus Stop has been suspended
  • Park Land area if licence is granted