100 Avenue Road – Project Update

Please see below for a project update that was circulated to neighbours on the 25th July 2022. Dear Neighbour, I am writing with an update regarding Essential Living’s development at 100 Avenue Road, above Swiss Cottage Underground Station. Following an 18-month period of main construction works being paused on site, I am very pleased to […]

Planning update: 19 January 2021

Camilla Lesser, Development Manager at Essential Living, said: “Essential Living is committed to delivering a high-quality new development at 100 Avenue Road and ensuring a positive and sustainable future for this accessible site. The principle of the development is established, and it is in everyone’s interest to see the site built out and making a […]

Construction Update: 8th Aug 2019

Progress over period (19/07/2019 – 08/08/2019) Structural demolition of existing ground floor slab On site crushing of hardcore resulted from demolition to minimise vehicle movement Breaking out existing foundations for piling works Installation of Temporary Works to support existing retaining works Excavations works Actions over next period (08/08/2019 – 08/08/2019) Breaking out existing basement slab […]

Construction Update: 14th May 2019

Demolition of level 05 to level 04 Scaffold removal from 2.4m above level 05 to 2.4m above level 04 Ongoing demolition of level 04 to level 03 concurrently with the scaffold removal around the perimeter Strip out works within the basement area currently at 90% Strip out works within the Ground Floor area currently at […]

Construction Update: 13th March 2019

Progress to date (11/03/19) LUL scaffold protection deck completed Site set up ongoing with the planned delivery of welfare cabins on 25/02/19 allowing JFH to release the ground floor area for service isolations, decommissioning and soft strip works to commence Hoarding erection completed, with 40% of the dibond cover already installed on the park side. […]

Construction Update: 30th January 2019

Progress over period (17/01/2018 – 24/01/2019) Site Set up Erection of hoarding Limited ground clearance Scaffold erection Internal strip-out of buildings Actions over next period (24/01/2019 – 07/02/2019) Completion of hoarding Installation of additional environmental monitoring equipment and hoarding lighting Service isolations and M&E decommissioning continuing within the building Continue scaffolding Continue internal strip out […]